Concrete tower in Benin
|
LV distribution in Maputo
|
SWER Line in Nepal |
Single Phase line and Single-Phase Transformer
|
|
|
|
Cost effective
electrical networks
Today many million people all over the world
rely on electric power which has been distributed over long
rural areas taking use of single-phase only. Over 20 years of
experience from developing countries also shows that
transmission tower shield wires can distribute significantly
amount of power at very low cost to rural and remote settings.
These facts, however, are still not very well communicated to
national utilities, project developers and donors, engaged in
rural electrification programs in poor countries. There are many
reasons behind this and some are explained in this paper.
Electrification is one
of the most important steps to enhance the standard of living in
developing countries. It is estimated that around 2 billion
people lives in areas without any electric power supply- most of
then in remote and rural areas. Electrification programs in many
developing countries have been undertaken during the last
decades but obvious the number of people in these countries
grows faster than present connection rates.
One reason for this
widening “energy divide” is the high cost to reach underserved
areas with electricity from existing national grids
(transmission and distribution) and the high cost for
small-scale local electricity generation by traditional models,
typically diesel gensets. It has been observed in many
developing countries that rural electrification is done using
the European (3-wire) or North American (4-wire) urban standard
design methods. Typically those consists of three-phase systems
with relatively high power transfer capability. It is not
uncommon that national utilities in these countries claim that
the cost per km grid extension often to exceed USD 20,000-40,000
per km, with yearly operation and maintenance costs as high as
5% of the investment.
However, rural
electrification programs have been implemented worldwide with
different results and with costs per km ranging from as low as
USD 3,000 per km.
(See a review of standard and low-cost options)The question is why not the least costs
solution are applied as they could bring forth an accelerated
electrification. Many reasons have been explained to this. For
example, there is a limited knowledge of the least cost
solutions as three-phase electricity is “supposed to be the only
alternative” for motors and other productive energy use. Further
appropriate energy planning methods don’t exists for low
consumption rural settings. The financing of electrification
programs have been made trough bilateral donor programs and
costs really not considered as the limiting factor. Early tests
with e.g. single phase systems failed, due to theft of earth
conductors etc.
The straight forward
approach of lowering cost of rural electrification is generally
very simple in its structure. I principle low-cost systems don’t
differ significantly from today’s three-phase-systems. One could
simply extend a system with one or two conductors instead of
three. Further, reducing the conductor area gives the
opportunity to increase the pole span, thereby reducing the
number of poles, insulators, stay wires, etc. with significant
cost reductions on both material, construction and maintenance
as a result. In case of using the earth as a return conductor
(SWER) very simple and cost-effective systems could be
developed.
Experiences from
low-cost and single-phase electric distribution
Today many countries
world-wide have adopted single-phase distribution systems
especially for connecting rural and remote areas. In the US,
which started already in the 20-ies there are now at least
100,000 customer relying on single-phase distribution only.
Most rural farms in the mid-west are still relying on
single-phase distribution.
In rural Australia, New
Zealand, Canada, Ireland and UK about 100,000 customer have
been smoothly supplied since the 50-ies. Recent electrification
in Cameroon, Cambodia, Tunisia, Morocco, Philippines, Benin,
Bangladesh, Bolivia, El Salvador and Brazil have connected
another 100,000 customers.
I South Africa ESKOM
adopted a single-phase strategy a few years ago for electrifying
rural areas like the Northern Province, Eastern Cape and KwaZulu
Natal. At present at least 100,000 customers have that
service.In both Ghana, Togo, Benin, Sierra Leone, Ethiopia, Laos
etc. single phase distribution has been applied using the shield
wires of existing transmission lines, thereby extending medium
voltage supply over distances around 100 km at extremely low
cost in existing transmission corridors. In total over 2200 km
of shield wires are in current use in these countries.
Experiences from
single-phase distribution are generally reported many times to
be superior of the three-phase systems. This is mostly due to
lower failure rates because of significantly lower number of
critical components and reduced mechanical stress.
Economics of low-cost and single phase
distribution
Single phase
distribution can be implemented in at least two different ways.
One is to bring out two conductors, instead of three. The other
is to use only one metallic conductor and use the earth as a
return conductor. The latter known as Single Phase Earth Return
System (SWER)
With good conductivity
of the soil the latter could typically transfer about 500 kW at
distances up to 25 km at voltages of 19.1 kV and an aluminum
conductor size of 75 mm2. Similarly a cheaper 22 mm2
steel conductor could transfer a maximum of 200 kW about 25 km
at 19.1 kV and a maximum voltage drop of 5%. Introducing modern
power electronic controllers (micro-FACTS) the extension could
be even longer as the voltage could be restored not to exceed
the 5-10 % tolerance limits.
Comparing cost for
implementing the single-phase systems rather than the “standard”
three-phase designs yields cost reductions down to about 40% of
the traditional cost.
In Table 1 a comparison
is given for three-phase designs at 33 kV and Single phase
designs using different conductor sizes and pole spans.
Table 1. Cost comparison of
three-phase and single-phase designs
Distribution System |
Cost
USD/km |
Capacity
kVA |
Pole span
|
Relative cost (%) |
MV System |
|
25 km |
m |
% |
Three phase, 3
wire, 33 kV |
|
|
|
|
Aluminum 148 mm2
|
20,000 |
8,000 |
120 |
100 |
Aluminum 100 mm2 |
13,950 |
5,000 |
150 |
75 |
Aluminum 77 mm2 |
11,000 |
4,000 |
225 |
59 |
Aluminum 34 mm2 |
9,000 |
1,500 |
225 |
48 |
Steel 25 mm2 |
5,800 |
600 |
300 |
29 |
Single Phase, 2
wire, 33 kV |
|
|
|
|
Aluminum 77 mm2
|
8,000 |
3,000 |
300 |
40 |
Aluminum 34 mm2 |
6,700 |
1,200 |
300 |
34 |
SWER, 1
wire, 19.1 kV |
|
|
|
|
Aluminum 77 mm2 |
4,500 |
500 |
300 |
23 |
Aluminum 34 mm2 |
3,850 |
400 |
300 |
19 |
Steel 25 mm2 |
2,300 |
200 |
300 |
12 |
Least cost options can
thus be found both among three phase system designs and by using
different single phase configurations and essentially by
changing conductor area and pole span with. For both three phase
systems with 25 mm2 conductors as well as single
phase designs, the pole span could be extend up to as much as
600 m, depending on the actual situation, thereby reducing costs
even further.
International Benchmark studies
A few years ago a study
was performed to compare costs for rural electrification in a
number of countries. The study showed a great variation of costs
between the selected countries. In Bangladesh e.g. costs could
be as low as $ 2,500 per km while in the US the cost could be as
high $ 25,000 per km. In figure 1 some comparative data can be
seen for both three-phase and single-phase systems. As import
duties, labor cost etc. varies between the countries it could
be hard to establish a world-wide cost standard. In Table 2 an
attempt is made to establish a average-low benchmark, based on
costs from Bangladesh.
Table 2.
Cost structure of a low-cost benchmark
Item |
Cost
($/km) |
10.5 m wood
poles
11@$170 |
1,900 |
Conductor 3 km
35 mm2 ACSR |
1,200 |
Poletop
accessories |
800 |
Guy assemblies |
500 |
Labor cost |
500 |
Total
cost: |
4,900 |
MV distribution based on data from
Bangladesh
Technology and market barriers much
related to perceptions
Despite the fact
that single-phase distribution have been applied on many
continents over the last decades there are little knowledge and
experiences of system behavior well communicated. Many
sub-Sahara utilities claim they tested e.g. SWER systems already
10-20 years ago but with bad results. Some claim that earth
conductors were stolen or vandalized, resulting in power outage
and safety concern. Some claim that the soil conditions were not
good enough for SWER to operate.
It is also a very common
perception that three phase systems are needed for the
productive uses like larger motors. The availability of larger
single-phase motors, up to 60-75 kW is typically not known. The
conceptual idea of mixing system designs between, urban ,
peri-urban and rural settings is not applied and most countries
apply a common urban standard, capable of transmitting many MW
of power, despite the extremely low loads. Very little effort
has been done trough donor and bank lending programs to adopt
new least cost designs, based on actual demands and more
conservative load prediction methods.
Reducing costs of electric distribution
systems
There are a variety of
approaches to reducing the cost of distribution lines, like
e.g.;
-
Appropriate design specification for
rural conditions
-
Standardized pre-calculated designs
including pre-qualified equipment and material kits
-
Better construction methods and simpler
procedures
-
Taking use of transmission towers for
Shield-wire distribution
-
Locally obtained alternative material and
components
-
Consumer involvement
More appropriate design specification
needed
One reason why rural
electrification in many developing countries exclude
single-phase system options is that planning criteria are
inappropriate. For example time horizons for load growth are set
to 25 years. Adding to this are also conservative design factors
for excess loads of wind, temperature and other mechanical
loads. In Burkina Faso it was found that transmission line
design was done according to European norms, thus allowing for
ice-loads. Obviously there is a need for revising the design
specifications to better comply with local climatic and
environmental conditions.
When aggregating rural
and remote loads it is further common to linearly add individual
loads without any statistical modification. Typically household
loads are oversized and combinatory effects from e.g. load
management are typically neglected. These factors all add to
heavily overestimate load and load growth.
Standardized
pre-calculated designs and simpler construction methods
including pre-qualified equipment and material kits
A method commonly used
to lower cost of electric distribution is to standardize designs
and only use these. The Swedish EBR system was e.g. adopted some
30 years ago and now all electric utilities refer to these
designs. However, the designs are not only pre-calculated
mechanically and electrically, but also specified when it comes
to physical design and material choices. The EBR design
guidelines consists therefore of a methodology in selection of
appropriate components, economic calculation models,
construction and installation guides, electrical safety notices,
maintenance instructions and pre-specified material kits. The
system is available both on CD-Rom, via Internet and in paper
format (manuals) as well as in MS Exel spreadsheets. It has
been estimated that the overall cost reduction by using this
rational system has been more than 50% over the last decades. A
suggestion is therefore to introduce a similar system for
low-cost rural electrification in Sub-Sahara.
Locally obtained
alternative material and components
To further lower costs
in rural electrification many components could be obtained
locally. This is especially true when it comes to poles and some
of the pole-top assembles. As poles contribute to the cost by up
to 20-30% or even more in case of high transportation cost, the
local supply of pole material is a critical factor that could
help lowering cost for rural electrification. It is supposed
that any rural electrification program should investigate
alternative pole manufacturing sources, close to the project
sites.
Consumer involvement
in reducing costs
As installation of rural
electrification systems are based on lower cost material the
proportion of the labor costs increases. Typically for a MV or
LV network the labor cost can be between 20-30 %. Involving the
consumer could lower cost further in many cases. As the
consumer has to take care of internal installation other cost
reducing methods could also be looked into. One example is the
local contribution of material and labor. In many rural settings
the contribution to installment of e.g. drop-wires and any
ground work as digging cable trenches, building transformer
houses etc. could be in kind contributions that boils down the
network installation costs to minimum.
A proposed strategy to introduce low-cost
rural electrification
Feeding LV customer with 1 kV cable connection
Calculation has been made which possible lengths 1 kV cables can be used too
feed small loads as e.g households, houses with battery charges etc. A fuse
to protect the
cable is needed. The feeding voltage is assumed 230 volts and voltage at the load is at least 180
volts. Surrounding temperature is 20°C.
No voltages drop in the fault location. Loads
characteristics is CosFi=1.
The breaker should have an A-characteristic curve. This breaker shall accept maximum
2-3 x In.
The calculation below gives longest lengths under best conditions.
Area, mm2, |
Circuit breaker
A-characteristic curve |
Maximum possible cable length |
Max
power |
2.5 |
1A |
Ca 3.3km |
180W |
2.5 |
2A |
Ca 1.6km |
360W |
2.5 |
3A |
Ca 1.1km |
540W |
|
|
|
|
5 |
1A |
Ca 6.6km |
180W |
5 |
2A |
Ca 3.3km |
360W |
5 |
3A |
Ca 2.2km |
540W |
5 |
4A |
Ca 1.6km |
720W |
5 |
6A |
Ca 1.1km |
1080W |
|
|
|
|
10 |
1A |
Ca 13.6km |
180W |
10 |
3A |
Ca 4.5km |
540W |
10 |
4A |
Ca 3.4km |
720W |
|
|
|
|
20 |
1A |
Ca 27.5km |
180W |
20 |
2A |
Ca 13.6km |
360W |
20 |
3A |
Ca 9km |
540W |
20 |
4A |
Ca 6.8km |
720W |
20 |
6A |
Ca 4.5km |
1080W |
20 |
10A |
Ca 2.8km |
1800W |
Current Limiters for Load Control
|
Current Limiter for low income consumers from Sustaianble
Control Systems Ltd. UK |
|
Copyright © 2004, StonePower AB |
|
|